Structural steelwork

Engineering, fabrication and installation of steel structures for stainless steel pipelines' scaffold bridge between the manufacturing shops

Subject: "Waffles Day and Night“
Year of completion: 2017
Scope of works: Engineering, fabrication and installation of stainless steel pipelines, pipe rack between existing and new manufacturing shop, insulated panels cladding.

Fabrication and installation of structural steelwork for technological tower

Subject: "Mondelеēz Bulgaria Production“ EOOD
Year of completion: 2016
Scope of works: Fabrication and installation of structural steelwork for chocolate storage tanks tower, supply and installation of roof and wall insulated panels, finishing assemblies.

Fabrication and installation of support structural steelwork for technological equipment for secondary electrolyte cleaning

Subject: „Aurubis Bulgaria” AD
Year of completion: 2016
Scope of works: Fabrication and delivery of support and auxiliary steelwork for technological equipment, erectiom of steelwork structures and equipment, fabrication and installation of pipe racks.

Complete construction of plant for raw oil production

Object: "New Oil" AD

Implementation period: 2014 - 2015

Scope: Fabrication and erection of steel structures for elevator tower, Mechanical installation of walkways , fabrication and erection of steel structure for "Pressing workshop" and "Unloading", scaffold bridges for steam Steel pipelines and heat Steel pipelines.

Fabrication of sheet steel structures

Object: "CBMI Construction Co. Ltd - branch Bulgaria" ENG

Implementation period: 2013-2014

Scope: Fabrication of gas ducts for project: "New production line of Devnya Cement".

Production of steel structures and port facilities

Subject: Production of steel structures and port facilities.

Implementation perios: 2013 - present

Scope: Production of sheet steel structures for protective panels ( fenders ), auxilliary structures for fender installation, trails and walkways, pipe steel structures for port facilities, etc.

Fabrication and erection of steel structures

Object: "Himmash" AD ENG

Implementation period: 2013

Scope: Fabrication, delivery and erection of supporting steel structure for polymerisation reactor with capacity of 13 m3.

Construction of "New lead production"

Object: "Metalstroy" AD

Implementation period: 2012 - 2014

Scope: Partial fabrication and complete installation of main steel structure, fabrication and and erection of steel structures for stair cases, platforms, handrails, floors of corrugated steel plate, installation of wall and roof cladding from trapezoidal steel plate.

Complete construction of installation for calcification of natural gypsum

Object: "Gips" AD

Implementation period: 2011

Scope: Fabrication and erection of main steel structure, installation of facade and roof cladding from trapezoidal steel plate.

Fabrication and erection of bearing steel structure

Object: "Kamenitza" AD

Implementation period: 2011

Scope: Fabrication, delivery and erection of support steel structure for brewery mash vessels at the territory of brewery "Astika".

 

Construction of mobile platforms for airlines servicing

Object: "Lufthansa Technik Sofia" OOD

Implementation period: 2009 - 2011

Scope: Fabrication and erection of steel structures for mobile platforms for airlines servicing.

Construction of new workshop "Material storage facility"

Object: "Rubin" AD

Implementation period: 2009 - 2011

Scope: Fabrication and erection of steel structures, storage silos for main and raw materials, installation of facade and roof cladding from LT steel plate.

Fabrication and delivery of steel structures

Object: "Alstom Bulgaria" EOOD

Implementation period: 2009

Scope: Fabrication and delivery of steel structures for platforms for TPP "AES Maritza East".

Construction of workshop "Extraction"

Object: "Biser Oliva" AD

Implementation period: 2009

Scope: Fabrication and erection of steel structures for workshop "Extraction".

Reconstruction of agregate АС72

Object: "Neochim" AD

Implementation period: 2008-2009

Scope: Installation of industrial pipelines and fixture from stainless steel for scaffold bridges and industrial equipment.

Expansion of port - Burgas

Object: Port - Burgas

Implementation period: 2005 - 2006

Scope: Installation of steel structures for loading and unloading wagons equipment.

Construction of New lead production

Object: "KCM" AD

Implementation period: 2012-2014

Scope: Complete performance of part "Mechanical-technological", installation of kiln, boiler, burners, vessels, gasducts and dust-collection equipment, condensers and deairators, all steel pipelines, pumps and fitting.

Erection of industrial installation and equipment

Object: "Energoremont Holding" AD

Implementation period: 2005

Scope: Construction of Condense- cleaning installation ( CCI ) of blocks №1 and №2 in TPP "Maritza East 2".

Construction of wave processing plant

Object: "ADF Bulgaria" OOD

Implementation period: 2005

Scope: Fabrication and erection of industrial water tank.