Project site: "CBMI Construction CO Bulgaria"
Year of completion: 2013-2014
Scope of works: Fabrication of gas ducts for “Devnya Cement new production line” project.
Structural steelwork
Object: "KCM" AD
Implementation period: 2012-2014
Scope: Complete performance of part "Mechanical-technological", installation of kiln, boiler, burners, vessels, gasducts and dust-collection equipment, condensers and deairators, all steel pipelines, pumps and fitting.
Project site: "KCM" АD
Year of completion: 2013
Scope of works: Fabrication, delivery and installation of dewatering bunker, flap, hydraulic station and steel pipelines.
Object: "Energoremont Holding" AD
Implementation period: 2005
Scope: Construction of Condense- cleaning installation ( CCI ) of blocks №1 and №2 in TPP "Maritza East 2".
Project site: "Saint Gobain Construction Products Bulgaria" ЕООD
Year of completion: 2013
Scope of works: Fabrication, delivery and installation of weight bunkers for automatic dosing of chemicals.
Object: "ADF Bulgaria" OOD
Implementation period: 2005
Scope: Fabrication and erection of industrial water tank.
Object: "FLSmidth Airtech" A/S
Implementation period: 2013
Scope: Fabrication of sheet and profile steel structures for gas ducts, compensators, gas duct supports.
Оbject: "ZKI Volta" OOD
Implementation period: 2013
Scope: Fabrication of sheet steel structures for cyclone batteries, control assembly and fabrication at company's workshop.
Project site: "КCM" АD
Year of completion: 2012
Scope of works: Design, fabrication, delivery and installation of sodium carbonate storage steel silo.
Project site: "Zagorka" АD
Year of completion: 2012
Scope of works: Design, fabrication, delivery and installation of 110m3 hot water stainless steel tank.
Project site: "Amylum Bulgaria" ЕАD
Year of completion: 2012
Scope of works: Fabrication and delivery of 6pcs of stainless steel and carbon steel tanks with the following capacity – 10m3 - 3 pcs., 20m3 – 1pc., 30m3 -1pc., 50m3 – 1pc.
Project site: "Hyundai Heavy Industries " АD
Year of completion: 2011
Scope of works: Fabrication, delivery and installation of 100m3 transformation oil storage steel tank.
Project site: "Gips" АD
Year of completion: 2011
Scope of works: Fabrication, delivery and installation of gypsum storage steel silo.
Project site: "Ognyanovo-К" АD
Year of completion: 2011
Scope of works: Fabrication and installation of petrocox storage silo for a second lime kiln.
Project site: "Kamenitza" АD
Year of completion: 2010-2011
Scope of works: Design, fabrication and installation of brewery pulp storage vertical silos, mounting of screw conveyors, equipment and automation.
Project site: "Rubin" АD
Year of completion: 2009 - 2010
Scope of works: Fabrication and installation of main raw materials steel storage vertical silos in a new “Materials shop” part of “Rubin” AD glass factory
Project site: "Balkanstroy" АD
Year of completion: 2009
Scope of works: Fabrication and delivery of 100m3 steel silos - 2pcs.
Project site: "Vito 95" ООD
Year of completion: 2009
Scope of works: Fabrication and installation of stainless steel tank for firefighting purposes.
Object: "Balkanstroy" AD
Implementation period: 2009
Scope: Fabrication and delivery of sheet steel plates for air carbon steel ducts for plant "Technogips".
Object: "HS Energienlagen" GmbH
Implementation period: 2008
Scope: Fabrication and delivery of air ducts and gas ducts for new biomass boiler at the territory of "Mondi Stambolijski" EAD.
Object: "Simex Trans" EOOD
Implementation period: 2007-2008
Scope: Fabrication and delivery of sheet steel structures for gas ducts and air ducts for TPP "AES Maritza East".
Project site: "Bulgargas" ЕАD
Year of completion: 2005
Scope of works: Fabrication of plate works for dust-collectors, final and complete assembly at the production plant of the company.
Subject: Fabrication of steel containers for modular asphalt-mixing installations
Year of completion: ongoing since 2017
Scope of works: Fabrication and installation of profile steel structures for the containers' frame, fabrication of platework for dividing chambers, rock wool insulation and trapezoidal sheets cladding.
Subject: Fabrication of 4 pcs of tubular steel pontoons
Year of completion: 2018
Scope of works: Fabrication of 4 pcs of tubular steel pontoons, anti-corrosion coating application, polyethylene protective boards installation.